OEE Calculator for Mining and Mineral Processing
For crushing, grinding and processing plants, in tonnes per hour rather than parts.
This calculator needs JavaScript. You can still read how the numbers are worked out below, including a worked example.
Your numbers
Updates as you typeYour result
Free, no sign-upGet your full OEE loss report
Your results as a PDF, with the on-stream factor and TEEP, plus our free OEE Loss Tracker (Excel) to log every period and line.
- Your result above stays free. You never need to sign up to calculate.
Your report is on its way.
Want help reading it?
Book a 30-minute OEE review with our teamWe've also emailed you the links.
How this OEE calculator works for Mining
OEE (overall equipment effectiveness) is the share of what a crushing and grinding circuit could have made at its rated rate, in the time it was planned to run, that came out right first time. It multiplies availability (run time ÷ planned production time), performance (actual rate while running ÷ rated rate) and quality (on-spec output ÷ total output). Planned shutdowns are left out of planned production time. The full method, including how to choose the rated rate and how batch plants are handled, is on the OEE calculator for process industries page.
OEE = Availability × Performance × Quality
Worked example
A crushing plant has a rated throughput of 600 tonnes an hour and runs through a 30-day month. In the calculator above this is the starting example: a period of 720 hours with 24 hours of planned shutdown, so planned production time is 696 hours. Unplanned stops take 90 hours, so the plant runs for 606 hours. It makes 296000 tonnes of ore, of which 284000 tonnes of ore are on-spec, against a rated rate of 600 tonnes of ore an hour.
| Factor | Calculation | Result |
|---|---|---|
| Availability | 606 ÷ 696 | 87.1% |
| Performance | (296000 ÷ 606) ÷ 600 | 81.4% |
| Quality | 284000 ÷ 296000 | 96.0% |
| OEE | 87.1% × 81.4% × 96.0% | 68.0% |
Against the whole 720 hours the plant ran 84.2% of the time (the on-stream factor) and TEEP is 65.7%. The planned shutdown is not an OEE loss, but it shows in these calendar-time figures.
The losses that matter in Mining
Mineral processing plants are exposed to harsh wear and to ore that changes from day to day. Throughput depends heavily on the feed, so performance is often the largest loss.
| Loss in Mining | Counted in | What it looks like |
|---|---|---|
| Liner and wear-part failures | Availability | Crusher and mill liners, screens and chutes worn out before the planned change |
| Blockages and chute hang-ups | Availability | Wet or sticky ore choking a transfer point and stopping the circuit |
| Conveyor and power stops | Availability | Belt, drive or electrical failures outside the plan |
| Harder or coarser feed | Performance | Ore that cannot be processed at the rated rate |
| Surge bin and downstream limits | Performance | Plant held back by the bin level or the next stage |
| Off-size and off-grade product | Quality | Product that misses the size or grade requirement and is reworked or stockpiled |
Measuring OEE properly in Mining
The rated rate depends on the ore, so state the ore type or hardness it assumes, and update it when the feed changes materially. Plants usually measure running time from the main drive or feed, not from shift records. Fixed plant (crushers, mills) is the natural fit for this calculator; for haul trucks and shovels, mining usually reports availability and utilisation separately, and OEE for mobile fleets is defined differently. Mining operations often look at availability and utilisation as two separate measures; OEE includes both and adds rate and quality.
What do published figures say about OEE in Mining?
Vendor figures for mining vary widely and the main academic study on shovel and truck fleets could not be opened (it sits behind a publisher login), so no mining benchmark is quoted. Useful context:
- Mining operations usually report availability and utilisation as separate measures, so a mining OEE figure only compares with another if both use the same definition of scheduled time.
- oee.com notes that the 85% reference applies to discrete manufacturing, not process industries. oee.com
For reference, the widely quoted 85% comes from Seiichi Nakajima's 1984 book on total productive maintenance as a minimum to strive for (90% availability, 95% performance, 99% quality), and oee.com notes it was set for discrete manufacturing. Across industries, Evocon's data from more than 3,500 machines puts the typical plant nearer 55–60%. There is no audited benchmark for any single industry, so judge your line against its own trend and keep the definitions the same each time.
How maintenance software helps
- Track wear parts (liners, screens, belts, chute plates) as assets with run hours, so changes are planned in the maintenance window.
- Record every stop with a cause code (liner, blockage, belt, power), so the few causes that cost the most tonnes are clear.
- Use condition monitoring readings from drives and bearings to schedule work before a breakdown, with work orders in one place.
More for Mining
- Maintenance software for Mining
- Preventive maintenance schedule for Mining & mineral processing
- OEE software
- Downtime cost calculator
- MTTR and MTBF calculator
- OEE calculator for process industries
OEE calculators for other industries
Not your industry? Pick another one below, or search at the top of the page.
Process plants: continuous and batch How it is calculated
- CementCement, glass, ceramics & building materials
- Steel and MetalsSteel, foundry, forging & metals
- Oil and GasOil, gas & refining
- Chemicals and FertilisersChemicals, fertilisers & petrochemicals
- Paper and PulpPaper, pulp & board
- Sugar and DistilleriesAgro, grain, edible oil & sugar
- DairyFood, dairy & beverage processing
- Food ProcessingFood, dairy & beverage processing
- API and Bulk DrugsAPI & bulk drugs
- TextileTextile & garments
Production lines: parts, packs and units How it is calculated
- Auto ComponentsAutomotive & auto components
- ElectronicsElectronics & electrical manufacturing
- FMCGFMCG & consumer goods
- PackagingPackaging, paper & printing
- PlasticsPlastics, rubber & polymers
- Tyre and RubberTyre & rubber
- PharmaceuticalPharmaceutical & biotech
Is your industry or kind of plant missing? Tell us what to add and we will look at building a calculator for it.