OEE Calculator for Mining and Mineral Processing

For crushing, grinding and processing plants, in tonnes per hour rather than parts.

This calculator needs JavaScript. You can still read how the numbers are worked out below, including a worked example.

Your numbers

Updates as you type

Time

All calendar hours in the period: 24 for a day, 720 for a 30-day month

Planned maintenance shifts and scheduled liner relines, left out of OEE

Liner changes beyond plan, chute blockages, feeder and conveyor breakdowns, power and water outages

Output

Rated throughput: tonnes per hour at the design ore type and hardness

Everything produced in the period, on-spec or not, in tonnes of ore

Tonnes that met the product requirement first time (for example crusher product within the size limit)

Your result

Free, no sign-up

Check the highlighted fields to see your result.

Get your full OEE loss report

Your results as a PDF, with the on-stream factor and TEEP, plus our free OEE Loss Tracker (Excel) to log every period and line.

  • Your result above stays free. You never need to sign up to calculate.

By submitting, you agree to be contacted about PlantOps360. See our Privacy Policy.

How this OEE calculator works for Mining

OEE (overall equipment effectiveness) is the share of what a crushing and grinding circuit could have made at its rated rate, in the time it was planned to run, that came out right first time. It multiplies availability (run time ÷ planned production time), performance (actual rate while running ÷ rated rate) and quality (on-spec output ÷ total output). Planned shutdowns are left out of planned production time. The full method, including how to choose the rated rate and how batch plants are handled, is on the OEE calculator for process industries page.

OEE = Availability × Performance × Quality

Worked example

A crushing plant has a rated throughput of 600 tonnes an hour and runs through a 30-day month. In the calculator above this is the starting example: a period of 720 hours with 24 hours of planned shutdown, so planned production time is 696 hours. Unplanned stops take 90 hours, so the plant runs for 606 hours. It makes 296000 tonnes of ore, of which 284000 tonnes of ore are on-spec, against a rated rate of 600 tonnes of ore an hour.

FactorCalculationResult
Availability606 ÷ 69687.1%
Performance(296000 ÷ 606) ÷ 60081.4%
Quality284000 ÷ 29600096.0%
OEE87.1% × 81.4% × 96.0%68.0%

Against the whole 720 hours the plant ran 84.2% of the time (the on-stream factor) and TEEP is 65.7%. The planned shutdown is not an OEE loss, but it shows in these calendar-time figures.

The losses that matter in Mining

Mineral processing plants are exposed to harsh wear and to ore that changes from day to day. Throughput depends heavily on the feed, so performance is often the largest loss.

Loss in MiningCounted inWhat it looks like
Liner and wear-part failuresAvailabilityCrusher and mill liners, screens and chutes worn out before the planned change
Blockages and chute hang-upsAvailabilityWet or sticky ore choking a transfer point and stopping the circuit
Conveyor and power stopsAvailabilityBelt, drive or electrical failures outside the plan
Harder or coarser feedPerformanceOre that cannot be processed at the rated rate
Surge bin and downstream limitsPerformancePlant held back by the bin level or the next stage
Off-size and off-grade productQualityProduct that misses the size or grade requirement and is reworked or stockpiled

Measuring OEE properly in Mining

The rated rate depends on the ore, so state the ore type or hardness it assumes, and update it when the feed changes materially. Plants usually measure running time from the main drive or feed, not from shift records. Fixed plant (crushers, mills) is the natural fit for this calculator; for haul trucks and shovels, mining usually reports availability and utilisation separately, and OEE for mobile fleets is defined differently. Mining operations often look at availability and utilisation as two separate measures; OEE includes both and adds rate and quality.

What do published figures say about OEE in Mining?

Vendor figures for mining vary widely and the main academic study on shovel and truck fleets could not be opened (it sits behind a publisher login), so no mining benchmark is quoted. Useful context:

  • Mining operations usually report availability and utilisation as separate measures, so a mining OEE figure only compares with another if both use the same definition of scheduled time.
  • oee.com notes that the 85% reference applies to discrete manufacturing, not process industries. oee.com

For reference, the widely quoted 85% comes from Seiichi Nakajima's 1984 book on total productive maintenance as a minimum to strive for (90% availability, 95% performance, 99% quality), and oee.com notes it was set for discrete manufacturing. Across industries, Evocon's data from more than 3,500 machines puts the typical plant nearer 55–60%. There is no audited benchmark for any single industry, so judge your line against its own trend and keep the definitions the same each time.

How maintenance software helps

  • Track wear parts (liners, screens, belts, chute plates) as assets with run hours, so changes are planned in the maintenance window.
  • Record every stop with a cause code (liner, blockage, belt, power), so the few causes that cost the most tonnes are clear.
  • Use condition monitoring readings from drives and bearings to schedule work before a breakdown, with work orders in one place.

More for Mining

OEE calculators for other industries

Not your industry? Pick another one below, or search at the top of the page.

Process plants: continuous and batch How it is calculated

Production lines: parts, packs and units How it is calculated

Is your industry or kind of plant missing? Tell us what to add and we will look at building a calculator for it.

Frequently asked questions

Is OEE the same as availability and utilisation in mining?
No. Mining usually reports availability and utilisation separately. OEE combines availability with the rate and the quality of the output, measured against planned production time.
What rated rate should I use for a crusher or mill?
Use the design throughput for the ore the plant was designed for, or the best rate the plant has sustained on typical ore. State the choice and keep it consistent.
Can I use this for haul trucks?
It is designed for fixed plant measured in tonnes per hour. For trucks and shovels, availability and utilisation are the usual measures.
What is a good OEE for Mining?
There is no audited benchmark for this industry. The 85% figure was set for discrete manufacturing, and across industries the typical plant is nearer 55–60%. Compare your line with its own trend, using the same definitions each time.
How do you calculate OEE for Mining?
Multiply availability (run time divided by planned production time), performance (actual rate while running divided by the rated rate) and quality (on-spec output divided by total output). Planned shutdowns are left out of planned production time.

Want help reading your OEE results?

Book a 30-minute OEE review with our team
PlantOps360

See PlantOps360 on your plant data

Book a 30-minute guided walkthrough tailored to your maintenance operations.

Personalized to your assets & workflows
See AI work orders & BI live
No commitment — bring your questions
Your details stay private. No spam, ever.