Vapour absorption chiller (LiBr) Preventive Maintenance Schedule and Checklist

The vapour absorption chiller preventive maintenance schedule from our task library: 7 checks and jobs, from daily walk-rounds to the annual overhaul, with the time each one takes and what to look out for.

A vapour absorption chiller preventive maintenance schedule lists the checks and jobs done on the equipment at fixed intervals, how long each takes, and in what order of frequency, so problems are found before the vapour absorption chiller fails. This page gives the schedule used in the PlantOps360 task library for vapour absorption chiller (libr), which follows common industry practice for general-purpose equipment. It is also searched for as VAM, vapour absorption machine, LiBr chiller, absorption chiller.

The maker’s manual and your site safety procedures always come first where they differ. Intervals set by law differ by state.

Vapour absorption chiller preventive maintenance schedule and checklist

How oftenTaskEstimated time
DailyRecord chilled water, cooling water and steam or hot water temperatures and pressures; check solution level, vacuum and alarms10 min
DailyCheck for leaks, abnormal noise and the operation of the burner or steam control valve5 min
WeeklyRun the purge unit as per the OEM and record the vacuum; check the purge pump oil level20 min
MonthlyCheck the solution and refrigerant pumps for noise, vibration and leaks; check the cooling water treatment and strainers45 min
QuarterlySample the LiBr solution for concentration, pH, inhibitor and contamination; check the purge pump oil and change it if needed90 min
Half-yearlyTest the safety trips: crystallisation protection, low refrigerant temperature and high generator temperature; check the controls and sensors150 min
AnnualAnnual service: brush-clean absorber and condenser tubes, eddy current test of tubes as per the programme, vacuum leak test, replace purge pump oil and valve seals960 min

Vapour absorption chiller maintenance frequency and yearly workload

At the estimated times, one vapour absorption chiller needs about 145 hours of preventive maintenance a year. The biggest single job is “Annual service: brush-clean absorber and condenser tubes, eddy current test of tubes as per the programme, vacuum leak test, replace purge pump oil and valve seals” at 960 minutes, done annual. Multiply by the number of units you have to see the workload for your plant.

FrequencyTasksTime per roundHours per year
Daily215 min91.3 h
Weekly120 min17.3 h
Monthly145 min9.0 h
Quarterly190 min6.0 h
Half-yearly1150 min5.0 h
Annual1960 min16.0 h

What goes wrong on a vapour absorption chiller without preventive maintenance

  • Tube fouling and corrosion
  • Vacuum loss from air in-leakage
  • Solution and pump faults
  • Crystallisation from control or power faults

What to watch between services

  • Temperatures and solution concentration
  • Vacuum and purge frequency
  • Pump and burner condition

Safety and statutory notes for vapour absorption chiller maintenance

Lithium bromide solution needs correct handling. Purge, inhibitor and tube cleaning follow the maker’s schedule.

Where a vapour absorption chiller preventive maintenance schedule is used

This equipment is used in the industries below. Each link opens the preventive maintenance schedule guide for that industry, and the maintenance software page where we have one.

Browse the full list of equipment preventive maintenance schedules (317 types).

Run this vapour absorption chiller schedule in maintenance software

In preventive maintenance software, each row above becomes a recurring task on the asset with its checklist, time estimate and parts. Tasks can be triggered by calendar date, running hours, meter readings or production cycles, each completed task is recorded with the person and date, and a failed check can open a work order. For the method behind it, read the guide to the preventive maintenance schedule, or use the free generator to get a 12-month plan for your whole equipment list.

Build my preventive maintenance schedule (free Excel)

Frequently asked questions

How often should a vapour absorption chiller be serviced?

In our schedule a vapour absorption chiller has 7 tasks: 2 daily, 1 weekly, 1 monthly, 1 quarterly, 1 half-yearly, 1 annual. The biggest job is “Annual service: brush-clean absorber and condenser tubes, eddy current test of tubes as per the programme, vacuum leak test, replace purge pump oil and valve seals”, which is done annual. Always follow the maker’s manual where it gives a different interval.

What is included in vapour absorption chiller preventive maintenance?

It covers routine checks and jobs such as “Record chilled water, cooling water and steam or hot water temperatures and pressures…”, “Check for leaks, abnormal noise and the operation of the burner or steam control valve”, “Run the purge unit as per the OEM and record the vacuum; check the purge pump oil level”, up to the annual overhaul or inspection. The full list with times is in the table above.

How many hours of maintenance does a vapour absorption chiller need per year?

About 145 hours per unit per year at the estimated times in our library, including the daily checks done every day. Use it to plan workload, not as a benchmark.

Is there a free vapour absorption chiller maintenance checklist?

Yes. The table on this page is a ready checklist. The free preventive maintenance schedule generator turns it into a 12-month Excel schedule for your list of equipment, with monthly workload hours.

Ready to run this schedule in software?

See how PlantOps360 turns these tasks into work orders and records.

PlantOps360

See PlantOps360 on your plant data

Book a 30-minute guided walkthrough tailored to your maintenance operations.

Personalized to your assets & workflows
See AI work orders & BI live
No commitment — bring your questions
Your details stay private. No spam, ever.